Referinte

COGENERATION AND COMBINED CYCLE POWER PLANTS

Client

              Project Description Energy-Serv Scope of Services

1.

        ROMPETROL – Refinery CHP (4,5 MW steam turbine cogeneration)Catalytic cracking section - Feasibility Study;

- General Design;

- Financing arrangement

2..

PEHART-TEC, Pulp & Paper Industry

CHP (7 MW GT cogeneration plant),(process steam supply) - Feasibility Study;

- General Design;

- Financing arragement

3.

MOTRU, Municipality

CHP (5 MW steam turbine cogeneration)(district heating system supply) - Feasibility Study;

- General Design;

- Financing arrangement;

- Procurement, Erection and    Commissioning of Plant

4.

INVESTOR , for the FOCSANI, Municipality

CHP (15 MW GT cogeneration plant)(district heating system supply) - Feasibility Study;

- General Design;

5.

VASLUI, Municipality

CHP (4 MW, steam turbine CHP- (cogenerare)(district heating system supply) - Feasibility Study;

- General Design;

- Financing arragement

6.

UNIT (Belgium)

WIENSTROM (Austria)

CC Power Plant  Progresu, 420 MW - Prefeasibility study for JV tender with S.C. Electrocentrale Bucureşti S.A. (ELCEN)

7.

UNIT (Belgium)

WIENSTROM (Austria)

CC Power Plant Fantanele, 118 MW -  Prefeasibility study for JV tender with S.C. Electrocentrale Bucureşti S.A. (ELCEN)

 

CHP RENEWABLE ENERGY PROJECTS

Client

Project Description

Energy-Serv Scope of Services

1.

                  SORTILEMN-Gherla CHP 1,6 MW ORC Cogen Plant - Feasibility study

- Project Financing

- Project management

- Project operation

2.              NIRAJ ACE-BRAD- Eremitu CHP 0,6 MW ORC Cogen Plant - Project financing

- Project  management

- Project operation

THERMA-CHEM TECHNOLOGY

 1.

CET HOLBOCA, IASI

coal fuel, 2×50 MWe

reducing CO2 emissions by 22,000 t / year
2.                         CET TURCENI    lignite fuel, 4×330 MWe increasing energy efficiency and reducing GHG emissions;
3.                   CET BUCURESTI SUD restoring capacity and availability of CET Bucharest South boiler 525 t / h, fuel oil, 3% Sulfur

The technology was successfully applied in other areas such :

  1. Greece (Motor Oil-Refinery),
  2. Croatia (Rijeka refineries Sisaksi),
  3. Bulgaria (Lukoil-Neftochim refinery),
  4. Romania (Rompetrol refinery-Petromidia),
  5. United Arab Emirates (UAE) ,
  6.  Saudi Arabia.